At the back-up's advancing end, the tail is carried forward with the heading. A cassette elsewhere releases the belt already threaded around its pulleys. The joint visible on a painted section keeps coming back around; it is not remade each time a support frame goes in. The crew eventually adds a new roll, and that is a separate stop with different tools and access. On the shift sheet I would give each activity its own line: tail movement, support, roll addition and repair.
A belt section withdrawn with a split joint tells more than the cover grade on its purchase order. Is the lift central or confined to an edge? Is there fresh paint or steel abrasion near the moving tail? Are return rolls carrying packed fines? Photograph the condition as found and retain the cut-out. Write down where the storage carriage stood at first alarm; after the belt is pulled through, that position cannot be recovered from the strip alone.
Send the belt route, storage travel, curve plan and muck samples with the enquiry
The heading has a rhythm that the fixed surface conveyor does not. TBM advance, idler installation, cassette payout and belt-roll insertion each have a different interval. Record them as separate activities. A long interval between new rolls is useful only if the available storage, safe support installation and tail control permit it.
A 1.5 metre ring is a measurement of excavation, not a joint schedule. The tail may advance through many rings before a new belt roll is needed. Meanwhile frames and idlers are fitted behind it. The safe way to fit them is set by the conveyor maker and the site's procedure, which may permit some work while the belt runs. Count that support work separately from isolated splicing stops in the programme.
Before the next roll is delivered underground, survey the splice stand area. The roll needs a feed path and the crew needs enough dry space to prepare and hold the ends. A cure that is specified for a particular press cannot be compressed to suit the next muck train. Record whether each joint was built during a planned addition or a breakdown; that distinction becomes useful when its edge is inspected months later.
| Event in the drive | What changes | Usually needs a new belt joint? | Planning record |
|---|---|---|---|
| TBM advances and tail follows | More belt leaves storage | No, on a continuous layout | Chainage and cassette position |
| Support and idlers installed | Belt gains a supported path | No | Installed frame chainage |
| Cassette reserve approaches limit | New belt roll is inserted | Yes | Roll ID and joint record |
| Damaged length removed | Finished loop becomes shorter | Repair joint may be needed | Cut-out and new length |
| Drive reaches final length | Storage and line are commissioned | Depends on final arrangement | As-built route |
Between a moving and a fixed pulley set, the cassette stores several folds of belt. The label might describe total belt held rather than available carriage stroke. As a rough drawing exercise, extending both strands of a conveyor route by one metre may use about two metres of stored belt. The actual reeving, transition and take-up arrangement settle the number. Request a diagram showing metres of route advance against carriage position.
A painted scale on the carriage is more useful than an advertised capacity alone. Mark the usable ends and the range needed to maintain tension. The rest is available to feed the heading, subject to belt stretch and any cut-out repair. When the ordinary loaded position nears one end, book a roll addition while the crew still has a controlled work window. Changing cover thickness cannot restore carriage travel.
| Storage question | Data to request | Why it matters |
|---|---|---|
| Rated belt length | Cassette reeving and capacity definition | Converts reserve into possible advance |
| Usable carriage travel | Stops and tension-control range | Shows reserve available for payout |
| Elongation allowance | Belt construction and operating tension | Keeps the carriage within range |
| Pulley package | Diameter, lagging and access | Determines bend duty for the joint |
| Next roll location | Delivery route and splice stand | Determines a realistic shutdown |
Each joint interrupts and reconnects the tensile members. Fabric steps and steel cord layouts need their own approved procedure. For a vulcanised splice, the press record and prepared ends matter as much as the material lot. Once running, the joint passes the cassette again every lap. The tally of these bend passages is governed by speed and hours, even during months when no additional belt roll is fitted.
At the cassette, measure the pulley beneath the first lifting step. Compare its actual diameter and surface with the finished belt and splice drawing, then check bearing condition. If damage occurs on only one shoulder, look for a corresponding frame contact. Take a full-width photograph before the old joint is removed. A narrow cut-out can erase the beginning of the fault.
The joint drawing must suit both belt tension and the smallest bend. Show the splice crew's actual workplace on the installation plan. If a temporary fastener is permitted for a recovery, the operator needs its approved duration and inspection points; exposed hardware may snag in the loop. Give each finished joint a number tied to its two roll IDs, crew and cure record. Those details are easier to capture on the day than during a later failure review.
| Joint option | Check before approving it | Watch during service |
|---|---|---|
| Vulcanised fabric step | Ply pattern, press and cure record | Lift at step tips or moisture entry |
| Steel cord vulcanised joint | Cord layout, gap and cure procedure | Cord exposure or local separation |
| Finger joint on suitable light belting | Minimum pulley and design strength | Finger-tip lift |
| Mechanical repair | Belt tension and permitted duration | Loose fasteners and snag risk |
The tail does not encounter a curve once. It advances along it while loaded and while the idler sequence behind it is being completed. A tracking adjustment at yesterday's chainage may tell little about the next section. Put the curve plan and the proposed tail positions on one drawing. The designer needs belt width, loading, tension, horizontal radius, vertical profile and the room available for transition sets.
Mark the rubbing edge and follow it through the arc under ordinary muck flow. Check each newly fitted tail frame for squareness before turning a take-up winch. Engineered curve arrangements vary: canted sets, load-sensing rollers or a booster drive may be in the design. Use its radius and tension plot for the belt width and load in front of you. More pull on the belt is not an alignment drawing.
| Alignment feature | Field evidence | Design or maintenance check |
|---|---|---|
| Horizontal curve | Persistent outer-edge polish | Radius, cant and tension window |
| Tail entering curve | Tracking changes after advance | New frames and tail orientation |
| Vertical crest | Belt lift or unstable trough | Loaded contact and approved hold-down |
| Vertical sag | High roller load | Spacing, bearings and frame strength |
| Return route | Fines or edge contact | Clearance through the full curve |
The spoil heap can hide the difficult material. Take a sample from the belt on a shift when clay and conditioner stay on the scraper. Record its wet mass per volume, the largest ordinary lump and the way it leaves the chute. Compare that with drained chips from another shift. The two may fill the trough similarly but behave very differently at the head and on the returning belt.
Uphill conveying adds lifting work to the drive. Use the measured density range to calculate both ordinary and peak cases. If the load rolls or slides, run the proposed inclination and belt face with actual muck. A sidewall or cleat may help on a designed section, but its weight and roots change bending and cleaning. A single messy shift is a poor basis for converting the full mainline to a raised profile.
A rhythmic knock from beneath the return may be a roller wearing a ring of carryback. Stop and scrape a sample, then look upstream at the head cleaner and its discharge tray. Replace a seized bearing, but also remove the deposit source. Near the tail, inspect the chute support for cobbles or metal jammed against the belt. A stationary fragment there can make a long cut in minutes.
| Muck state | Carrying-side question | Return-side evidence | First response |
|---|---|---|---|
| Dry angular chips | Lump impact and fill level | Loose chips in roller nip | Support and controlled cleaning |
| Conditioned clay | Release at discharge | Sticky band on return rollers | Cleaner and drainage trial |
| Mixed face with cobbles | Peak lump and point load | Intermittent gouge | Inspect chute and impact bed |
| Water-rich fines | Trough stability and spillage | Slurry near bearings | Contain and drain |
Choose the tensile member from force and allowable stretch, then put the smallest loop pulley beside the proposed finished thickness and splice. The cover has a separate job: carry the sampled muck and survive the specified cleaning. Increasing the ply count may make a small cassette bend more severe. A frame scrape remains a frame scrape whatever is written on the belt label.
The related product pages can supply EP and steel cord construction data. For this tunnel, overlay their limits onto the calculated route and the pulleys already installed. Ask the fire-safety team which standard and evidence the contract requires underground, then include the exact grade and test in the order.
| Question to settle | Where to take the detail | What the tunnel drawing still needs |
|---|---|---|
| Carcass and tensile rating | Steel cord or EP construction data | Route tension and minimum pulley |
| Cover and cleaning | Compound and inspection data | Wet and dry muck exposure |
| Fire performance | Project requirement and test evidence | Location and installation duty |
| Joint life | Approved splice method | Cassette bends and safe work area |
Plot the first and final conveyor routes against TBM chainage. Add tail advance, support installation and the point at which stored belt is replenished. Lay the horizontal and vertical curves over that plot. With the wet and dry muck cases, the engineer can calculate tension, choose drive locations and check storage travel. The belt proposal then has an actual pulley and load schedule to answer.
The first enquiry can fit on one sheet: driven length, width, peak rate, largest lump, horizontal radii and gradient. Attach another drawing for storage reeving, carriage marks and the smallest bend. Add wet bulk-density results and a photograph of the space where the press will stand. The supplier can then specify a belt and joint against a real route rather than a width alone.
| Enquiry item | Site evidence | Acceptance question |
|---|---|---|
| Advance and storage plan | Chainage schedule and cassette drawing | When is a roll actually added? |
| Alignment and gradient | Horizontal and vertical survey | Where is special curve support needed? |
| Muck envelope | Samples and peak-feed record | What is the worst ordinary load? |
| Belt and pulley package | Calculated tension and diameter list | Does the joint clear every bend? |
| Safety and maintenance | Project rules and access plan | Can inspection and splicing be done safely? |
Send the alignment, advance plan and storage drawing for a belt-and-loop review
Usually when another roll is introduced or a damaged section is cut away. Advancing the tail can use belt already held in the cassette. Check the installed system's procedure and keep separate counts for advance, support work and roll insertion.
The first sign is often a carriage close to its permitted limit. Read its scale under the normal load and arrange the next roll insertion before the tension control loses its working travel. Calculate reserve in stored belt length, then convert it to route growth from the actual reeving. Keep elongation and repair allowance in the calculation.
Not as a blanket adjustment. Radius, idler geometry, loaded belt shape and the tension window must be engineered together. Extra force can raise edge and joint loads without correcting a skewed support. Check the installed frames and the designer's curve plan; booster drives may be part of a long curved system.
It passes every cassette pulley on each circuit. A small or worn pulley can flex the joint harder than the main drive does, while an edge rub may start the separation. Compare the actual diameter with the maker's minimum for the finished belt and joint, then examine both faces and the joint record.
Possibly. Wet conditioned muck changes fill, adhesion, carryback and sometimes load. Measure the operating range before choosing a cover or cleaner. A smooth surface may help release material in one application; impact and cut resistance may dominate where cobbles appear. The return arrangement and drainage belong in the selection too.
The painted joint number, adjoining roll IDs, date, crew, cure record and chainage. Add a close photograph when a step begins lifting. That is enough to compare planned roll additions with emergency repairs later.